New Daycare Center Bachzwerge

New construction of a day care center with 2 kindergarten groups and 2 nursery groups
(PV 9.72 kWp, battery storage 10.24 kWh, inverter 10.3 kW)

Architects HAAS + HAAS Architect | Urban Planner | Engineers

 

Landscape Architect Wolfgang Leimeister

 

Health and Safety Geisel Schaub Architekten GbR

 

Tragwerk WSP Ingenieure GmbH & Co. KG

 

HVAC, Electrical Engineering Planning Engineering Office Köberlein GmbH & Co. KG

 

Renninger Fire Protection Planning GmbH

 

Civil Engineering Office Köhl Würzburg GmbH

 

Soil expert ISU Umweltinstitut GmbH

 

Energy Concept Engineering Office for Energy Consulting Dipl. Ing. Anja Wunderlich

Launching in February 2022

 

Funded with 2.40 million euros by the Free State of Bavaria and the Federal Ministry for Family Affairs, Senior Citizens, Women and Youth.

The costs are estimated at 3.24 million euros.

Construction of a new daycare center with 2 groups and 2 nursery classes

 

Daycare Bachgasse 35

09.09.2023

Inauguration of the Bachzwerge daycare center.

 

In brilliant sunshine in Rimpar, the new day-care center was officially inaugurated.

 

For the official inauguration, Mayor Bernhard Weidner was able to welcome, among others, the Bavarian State Minister for Digital Affairs Judith Gerlach, Member of the Bundestag Paul Lehrieder, District Administrator Thomas Eberth, Deputy District Administrator Karen Heußner, and mayors of neighboring municipalities.

 

Afterwards, the doors were open for viewing and the venue's team offered a great supporting program.

 

A true jewel that all contributors and participants can be proud of. For that, we say THANK YOU.

 

We wish the children and the team a wonderful time in kindergarten in their new „home“ 🙂

01.09.2023

The time has come. We are very pleased to celebrate the opening of the Kita Bachzwerge day care center and invite all interested citizens.

 

When? Saturday, September 9, 2023, from 3 p.m. to 5 p.m.

 

Where? At the Bachzwerge daycare center, Bachgasse 35, 97222 Rimpar

 

Our guests, both young and old, can look forward to:

 

– Children's interactive activities
- Game scores and creative activities
– Bratwurst
– Coffee & Cake
– Ice

 

We look forward to seeing you 🙂

11.07.2023

The interior and exterior of the „Kita Bachzwerge“ daycare center are continuing to take shape.

 

More planting was done outside.

 

The Kiss & Go parking spaces, the sidewalks, and the bus stop are in the final stretch.

 

Inside, final construction cleaning is currently underway.

10.07.2023

The shrine was also re-erected.

07.06.2023

Inside:

 

- the flooring is completely installed
- the door frames and interior doors are installed on the upper floor
– the built-in wardrobes on the upper floor are installed
– the kindergarten kitchens are installed
– the various child seat benches by the windows are manufactured
– the lamps are in final assembly
– the cloakrooms in the kindergarten area are installed
– the balcony area is paved with slabs
– the main entrance door and the interior door are installed

 

External:

 

– the entrance area is paved and landscaped 
– the mailbox stele is installed
- trees and shrubs have already been planted
– the fall protection area and sandbox area are completely constructed
– access to the stream has been established

11.05.2023

A lot has happened in recent weeks and months:

 

Inside:

 

  • The interior window sills are installed
  • the wood acoustic ceilings are being installed
  • The walls are in the final stage of production  
  • The sanitary area for the kindergarten and nursery is awaiting the final installation of the sanitary fixtures.
  • The flooring work has begun.
  • The staircase is tiled
  • the electrical distribution boards are being assembled
  • the first switches and sockets are installed

 

External:

 

  • The wall panels on Austraße and in the entrance area have been installed.
  • The seating blocks and the steps at the entrance have been manufactured
  • The paving slabs for the terrace have been installed, including the drainage channels.
  • The enclosures for the play equipment and sandboxes are under construction
 

29.03.2023

– the wall paneling and the changing tables in the nursery restroom boxes on the ground floor are being implemented

22.03.2023

Since the beginning of the year, a lot has happened: screed work and drying have been completed, the installation of the sun protection on the street side is finished, the scaffolding on the street side has been dismantled, facade work on the street side is done, the drywall partitions have been erected, the rough electrical installation is complete, the interior walls have been plastered and prepared for the final coat of paint, the interior window sills have been installed, and work on the curtain-type ventilated facade and the steel staircase with railing is in the final phase. Meanwhile, the wall and floor tiles in the sanitary areas have been laid, and work on the suspended ceilings has begun. Landscaping (GaLa) work has started on the street side.

01.03.2023

– the wall and floor tiles in the sanitary areas have been laid and work on the suspended ceilings has begun

31.01.2023

-the screed work has been completed and the drying process is already underway

 

- the installation of the sun protection on the street side is complete

 

-the dismantling of the scaffolding on the street side is complete

 

- the facade work on the street side is done

 

-the drywall partitions are largely closed and in preparation for the subsequent painting work

 

- Work has begun on the ventilated curtain wall and the steel staircase with the railing.  

07.12.2022

Meanwhile, the interior plastering work has been completed. The insulation under the screed and the underfloor heating are being installed.

04.11.2022

Interior work is currently underway, including electrical installations, pre-wall installations, ventilation installations, and drywall construction.

03.08.2022

All the window frames are now set and the glass inserts installed.

29.07.2022

Installation of the large window frames (wood-aluminum) and glass panes

05.07.2022

Meanwhile, the tiles have been applied to the roof of the kindergarten in Bachgasse. The work is on schedule, and interior construction can begin soon.

17.06.2022

Topping-out ceremony at the daycare center in Bachgasse in Rimpar

 

Another milestone for child care in the market town of Rimpar has been reached. In wonderful summer weather and with everyone in high spirits, the topping-out ceremony for the kindergarten in Bachgasse in Rimpar was celebrated just four months after the groundbreaking.

 

With a triple hip-hip-hooray for children, master builders and builders along with the shards of glass from emptied champagne glasses, good fortune is to move into the new daycare center building. During the topping-out speech, master carpenter Manuel Weißenberger thanked those in charge for hosting the topping-out ceremony. „A tradition that is maintained less and less. It is meant to be a „thank you“ to all the tradespeople involved in the construction,“ said Weißenberger. „The topping-out tree used to be decorated by virgins. In the past, instead of ribbons, small pouches containing the wages for the tradespeople were hung on the tree. The topping-out ceremony means that the structural engineer is now finished, the supporting framework is up, the construction is complete,“ said Weißenberger. Finally, he also presented chains to Mayor Bernhard Weidner and Birgit Kiesel from the Construction and Planning department. Another custom: Walking through the building with the chains clanking is said to ward off misfortune, such as lightning strikes, etc., and drive away evil spirits. 

 

„Just recently we had the symbolic groundbreaking ceremony and a good four months later we are already celebrating the topping-out ceremony,“ said Mayor Bernhard Weidner. „Everything is on schedule and within budget.“ In this context, he expressly thanked his predecessor, Burkard Losert, who conceived this project and carried out the land acquisition. He emphasized the good and smooth cooperation between the municipality and the construction companies, which has contributed and continues to contribute to the rapid construction process and thus to the success of the project.

 

„As a municipality, we are glad that the number of children in Rimpar is growing and the day-care centers are accommodating more and more children,“ Weidner said. The stated goal of the municipality is for the children currently accommodated in emergency groups to move into the newly created rooms by the start of the 2023/24 kindergarten year, and for further capacities to be created as well. There is currently an emergency group for the nursery at Rappelkiste and an emergency group for the kindergarten at Kunterbunt Kindergarten.

 

In total, there will then be room for 50 children in two kindergarten groups and for 24 children in also two nursery groups. The costs are estimated at 3.24 million euros. Of this, 2.40 million euros will flow back to the municipality in subsidies and funding as part of the „Childcare Financing“ investment program. Rimpar already has four municipal kindergartens—the Schlossmühl, Schleifweg, Schäferei, and Waldkindergarten—all of which, except for the forest kindergarten, include nurseries.

Text and photos: Nadja Kess

24.05.2022

...and on we go with the walls and reinforced concrete columns on the ground floor... ring beams are being laid and integrated... the scaffolding is being erected...

10.05.2022

Meanwhile, the formwork for the ceiling above the ground floor has been removed. Next, the steel columns on the upper floor will be reinforced and the masonry walls erected. The tie beams in the stairwell have been concreted and the thick coatings are being applied.

28.04.2022

Meanwhile, the ceiling above the ground floor has also been installed.

19.04.2022

The ground floor is taking shape. All the walls there have now been constructed, so the ceiling above the ground floor can be poured with concrete very soon.

28.03.2022

The next milestone has been reached. A lot has happened with the new kindergarten building on Bachgasse since the groundbreaking ceremony. The main utility lines and foundations have been installed, the floor slab has been poured, and the first walls of the ground floor have also been put up.

22.02.2022

Construction work for the new kindergarten in Bachgasse in Rimpar is getting underway. For the symbolic groundbreaking ceremony, those who recently gathered included (from left to right): Simon Knobling (Weipert-Bau GmbH & Co. KG), Stephan Haas (Haas + Haas Architect/Urban Planner/Engineers), Rimpar's Mayor Bernhard Weidner, the Head of the Building and Planning Department in the market town of Rimpar Marco Göbet, Birgit Kiesel from the Building and Planning Department of the market town of Rimpar (Building Construction), Irina Köberlein (Köberlein Engineering Office) and Alexander Kress (WSP Ingenieure GmbH & Co. KG). Completion of the building is scheduled for the start of the 2023/24 kindergarten year. In total, there will then be room for 50 children in two kindergarten groups and 24 children in another two nursery groups. Costs are estimated at 3.24 million euros. Of this, 2.40 million euros will flow back to the municipality in grants and funding as part of the „Childcare Financing“ investment program. Back at the market town council meeting on December 13, 2018, the market town council unanimously approved the determination of need. Rimpar already has four municipal kindergartens—the Schlossmühl, Schleifweg, Schäferei, and Waldkindergarten—all of which, except for the forest kindergarten, include nurseries. The demand for childcare places in Rimpar has increased, not least due to the fact that in Bavaria every child from the age of one is entitled to a childcare place. Capacity utilization in the day-care facilities is gradually reaching its limits.

Opening hours today

The town hall is open today at the following times:

08:00 - 12:00

Do you have any questions or suggestions?

Then simply contact us at any time using the following contact options: